Middletown Elementary School Expansion
Frederick County Public Schools is committed to providing high-quality learning environments that support student success now and in the future. The Middletown Elementary School expansion is an important investment in our growing community, designed to create additional space, enhance instructional areas, and improve the overall school experience. We understand that construction while the school is occupied requires careful planning, and we are working closely with school leadership and our construction partners to ensure that safety, communication, and continuity of learning remain our top priorities throughout the project.
Project Overview
The Middletown Elementary School expansion includes adding a new gymnasium and 12 classrooms, repurposing the existing gym into new art and music classrooms, and expanding the cafeteria.
Howard Shockey and Sons is the low bidder.
Frequently Asked Questions
- Why is the school being expanded?
- What work is currently taking place?
- Is it safe for students and staff while construction is underway?
- How is the construction area separated from the school?
- What safety measures are in place during construction?
- Will construction impact air quality inside the school?
- Will construction take place inside the building?
- How is noise and disruption managed during the school day?
- How is construction coordinated with the school day?
- What happens if an issue arises during construction?
- How are concerns or unexpected issues handled?
- Who oversees the construction project?
- Are there regular safety inspections?
- How is the project monitored to ensure quality and safety?
- New Panel
- What measures are in place if a safety concern arises?
- How is the school minimizing impact on learning?
- Why does construction take place during school hours?
- Will construction impact students during the school year moving forward?
- How is the surrounding community being considered?
- How will families and the community stay informed about progress?
- Who can I contact if I have questions or concerns?
Why is the school being expanded?
What work is currently taking place?
Is it safe for students and staff while construction is underway?
How is the construction area separated from the school?
What safety measures are in place during construction?
Will construction impact air quality inside the school?
Will construction take place inside the building?
How is noise and disruption managed during the school day?
How is construction coordinated with the school day?
What happens if an issue arises during construction?
How are concerns or unexpected issues handled?
Who oversees the construction project?
Are there regular safety inspections?
How is the project monitored to ensure quality and safety?
New Panel
What measures are in place if a safety concern arises?
How is the school minimizing impact on learning?
Why does construction take place during school hours?
Will construction impact students during the school year moving forward?
How is the surrounding community being considered?
How will families and the community stay informed about progress?
Who can I contact if I have questions or concerns?
Project Timeline
- Task Order Contract A&E firm hired - Complete
- Design begins - Complete
- Schematic Design complete - Complete
- Design Development complete - Complete
- Construction Documents complete - Complete
- Bidding begins - Complete
- School Board selects contractor - Complete
- Construction begins - March 2026
- Construction complete - May 2028